UK Railways : Derailed for good ?

The last few years have been a sorry tale for the UK rail industry. With periodic train crashes across the network, there have been calls for the whole network to be brought back under the control of the public sector - not that such a 'buy-back' is financially feasible anymore.
  Today, the UK rail network is suffering from over 50 years of under-investment and utter neglect, as a result of every single UK post-war government. There is though a lot of 'work in progress' in the current rail network, and it could be said that in 15-20 years the UK rail network will be relatively stunning compared to its current state. 


Stretched to capacity

  In January of 2003 the UK rail operators agreed to actually cut back on some services, in order to make the service more reliable. It is clear that over the last few years as passenger numbers have increased (as UK government policy intended) that the rail network has reached its full capacity. With current technology and other aspects considered, it is simply not possible to cram any more trains on to the existing network.
  With this fact in mind, it is therefore necessary to face the necessity of expanding upon the existing network, not simply ploughing more money into what already exist.


A Metro underground system for the UK

   I have always been impressed with the London Underground, structurally speaking that is. The London metro system runs for 243 miles of which approximately 42% is tunnelled rail. It is also useful to realise that the London network continues to expand, this is especially true for lines in the east end of London. The actual operation of this underground metro system does leave a lot to be desired though, and I believe is poorly managed. However the actual engineering of the underground itself remains hugely impressive. This is especially so when consideration is given to the fact that most of it was dug out a century ago.


A Bold proposal for the 21'st century

  As things are, as long as the current UK government's investment in transport policy is followed through this decade, the quality of existing transport network should improve - if somewhat slowly. However, we cannot ignore the fact that the overall transport network is already bursting at the seams.
   I believe it is time for the UK to have a new high speed mass transit link. This high speed link would connect all the main UK population centres together. Currently, both the road and rail network are already beyond their rated capacity. It is simply not feasible to expect any more trains or cars to use the existing transport links. What is instead required is an additional transit link network. 


Lets Go Underground



A typical tunnel boring machine- Yucca Mountain, USA


   A high speed link underground, does that sound crazy ? Well, there is already a precedent of course,- the channel tunnel link. The 'Chunnel' stretches for 31 miles, which makes it one of the longest tunnels in the world. The idea of a tunnel running 102 miles might seem truly mad though. However, again there is a precedent - the London underground network (tunnelled section) amounts to around 140miles. So, the issue is not whether the project can be done, but if it should be done.

Benefits of Underground tunnelling

- Planning/legal issues, far simpler, less prep. time needed
- No issues about building near housing/industry.
- Travel, the quickest route is possible via a 100% straight route.


Flying trains
 
  The days of trains with screechy wheels, and track which must regularly replaced, are coming to an end. Any new transit 'rail' system must be progressive, Magnetic-levitation (Maglev) technology is the only way to proceed in this respect.
    Maglev transportation has finally come of age. China has recently shown the way ahead in terms of mass transportation. The new shanghai-Pudong Intl. Airport link has just been completed, and is probably the most advanced means of transportation in the world. Using Magnetic levitation the train carriages float just a fraction of an inch above the track. The trains can reach astonishingly fast speeds of 440kmh (273mph) and even faster speeds are possible where the track is straight.
  At Lathen in north-west Germany in the past 14 years; they have been test-operating maglev trains, which over the years have clocked up more than 700,000 kilometres in trials. The German maglev train has a maximum design speed of 550kmh (that is 341mph !).  
   In fact, there is no real limit to how fast these things can travel. In Japan, 2 maglev trains passed each other, each travelling at over 500kmh, meaning a relative speed contrast of over 1000kmh ! Amazing indeed, and the technology is continuing to be refined and improved. With the Chinese leadership's decision to invest in Maglev transit (possibly nationwide), the technology is sure to improve at an even faster rate over the coming years.

 
Driverless trains

  With the level of technology as it is, there is absolutely no need for train drivers. For instance, just look at how well London's Docklands light Railway operates. Not a single driver on any of it's network, everything is run at special control centres.
   It makes no sense to pay people to drive trains, when it can be all done from a central/regional command centre. In order to maximise the number of trains on the line at any one time, a fully computerised system is the only way to fully utilise the capacity of the new lines. Arguably, having computers take over the control of trains is more safe than leaving it to humans, who inevitably make errors from time to time.


Engineering on a Grand Scale

   I envisage a countrywide engineering plan, on a scale that even the great engineer Brunel would be proud of. Once the first link has been completed, the shear popularity and speed of the line will see the mass population demand a nationwide network be established. Public support for such a new method of transit across the UK will be necessary if the project will become self-financing in the longer term.
   The task involved in boring such long tunnels will be no different than that involved in any other major tunnelling project. The technology is available now, both the ability to tunnel efficiently and the new Maglev mode of travel are ready to be applied. The overall plan I propose can be split into two main stages.


The Beginning

  Stage one of the overall plan calls for a London-Birmingham link. Birmingham is arguably the second capital of the UK, and thus merits the primary stage of the plan. The link itself would amount to a distance of around 102 miles. This would indeed be the longest man-made tunnel in the world. Note that exact distances are based on straight line links, precise numbers would depend on where each mainline station would be placed in each city.

Station location.
 
   The stations themselves should be as close to the centre of the main population centres as possible. Other mitigating issues are of importance though. The stations should be close enough to existing primary transport hubs. In the case of London, it would be very tempting to locate the Station in the Kings X/Euston area, rather than the actual city of London itself.  In any case, the station would be need of a significant size, in order to meet the expected passenger numbers.  The station structures could be based entirely underground, or a combination of surface/sub-surface design.


How fast can tunnelling proceed ?

   Tunnelling speed depends on a variety of factors, not least of which is the material being drilled through. However, a rough guide can be used to formulate some initial time line of events.
  The British-French channel tunnel was constructed at a rate as high as 250ft per day. A review of companies specialising in tunnelling, suggest a daily tunnelling rate of around 150-250feet a day. This equates to about 0.0474 miles per day. Assuming a 5 day standard week, that is 0.237 miles per week. Assuming 50 weeks of tunnelling a year that is 11.85 miles a year.

   For this project to work, multiple teams will need to be in place. I suggest a minimum of 3 teams to complete this first stage. Each team completing roughly a third of the 102mile route.

   Noting that one team will likely tunnel around 10-12 miles a years (assume a conservative 10 miles per yr), a distance of around 102 miles will take the three teams about 3.5yrs.
Personally, I think 3.5 years is extremely fast for such a project.

   Station construction will in itself take a few years, although this should be run concurrently with the main tunnelling teams.    
   Overall, I would argue that the project should take no more than 4-5 years to complete. Planning issues, surveying, and other preliminary assessments should be permitted to take no longer than 2 years.

* Note that the 'tunnel' is actually comprised of  3 actual tunnels, 2 main ones for the actual passenger trains, with a service tunnel between them. This is exactly the same configuration as used in the Channel tunnel, offering a reliable means of maintenance and safe escape.

 
Stage 2 and Beyond

  As the final sections of the London-Birmingham link are being completed, a new team should already have begun to extend the line from Birmingham northwards to Manchester.
Assuming 2 teams working on this link, we are looking at around another 3-4 years for this link to be completed.

Linking the Far north of the UK to the capital is going to be an almighty task for the engineers to complete. To complete a London to Glasgow link, we are looking at a time span of somewhere on the scale of 12-15 years.

Cross linking other smaller cities will then become the next task for constructors. Connecting up all the main population centres, including Leeds, Liverpool, and Nottingham and other nearby cities.
Also, a new link from London westwards should be established running along the main M4 'urban corridor', all the way to Cardiff.


Financing the UK Metro Plan

   The plan outlined is indeed bold, but how much would this cost the UK taxpayer ? Would such costs be justified by benefits to the UK traveller and economy as a whole ?

The channel tunnel cost £9 billion (at 1994 prices) for the 31mile stretch. What could we expect the London-Birmingham link to cost ?

As an amateur economist (amongst other things) I would suggest at least £15 billion per 34 mile section. Hmm, how does that sound ? That makes a rough figure of £45 billion for the first stage of the overall plan.

Personally, I consider ALL expenditure on such grand engineering projects as entirely justified. Once built, the network will last for centuries. The running costs of the network once built would be made to be self-financing. Commuting fares should be representative of the investment in the line. 

Economically speaking, long term borrowing for capital investment can be justified - although allocated investment must be efficiently used.

Once Stage 1 is complete, and is fully operational, ALL income from commuters should be set aside to finance the costs of further development.

Other options ?

  It is of course possible that other network options could be selected. A combination of tunnelling and surface rail perhaps. Surface rail would be much cheaper, however the logistics of building a new surface line are complex and opposition to building anything anywhere in the UK would make the Maglev plan potentially bogged down in a bureaucracy of planning groups.
  The simplest way to connect two places in a highly urbanised country will forever be a straight line tunnel. 
 

The Future of UK Transport


   The future for the UK transport network could be a spectacular one, or it could remain as it is, stretched to capacity, poorly managed, with relentlessly poor levels of capital investment. What seems paramount right now are new transport links.
   A nationwide Maglev transit system would provide for the first time, the means to get to other cities almost as quick as travelling by air. The construction costs involved are indeed immense, and would constitute the single largest capital project ever attempted in the UK. Yet the UK commuting public are aching for a decent transport network. The benefits in less congestion are clear. The ability to hop on a train and cruise across the UK at 300mph cannot be overstated. The UK commuter deserves a new means of transport, Maglev seems the most logical option to take.
 
   What I have proposed here in this summary article, may sound far fetched and unachievable. Yet the Channel tunnel was completed with immense engineering success, despite the many people who once said it could never be done. The UK public deserve a metro system fit for the third millennium, not the 19'th century. It is time to expand the UK transport network, it is time for the UK Metro system.
 

Contact Calrissian

Return to 

© 2003 Philip Calrissian
Last Updated : 04/01/05

 



World Population : 6.27 billion as at Feb 4'th 2003

US/World population clock
 


Artist impression of Shanghai express
Photo : www.transrapid.de.

 

 

 



Related Websites


Network Rail : Non-profit company managing the UK's rail network of tracks and stations

SRA- Strategic Rail Authority, for the UK's network

Dft - Dept for Transport : UK' govt. website.

State of the Railways : BBC online rail section

 

 

 

 

 

 

 

 

 

 

 


Special articles

Transrapid Intl : Flying on the Ground

Wonders of the World : The Channel Tunnel

Rail Technology : Beijing-Shanghai high speed link









 

 




Shanghai, China : Mag-Lev station
 

 

 

 

 

 

 


Artist conception of interior of a 'regional express'
Photo : www.transrapid.de
 

 

 

 

 

 

 


Stage 1 : Southern Metro Plan
 




Distances involved (as the crow flies)

London-Birmingham : 102 miles
Birmingham - Manchester : 70 miles

 

 


Stage 2 : Midlands/North Metro Plan


Distances involved (as the crow flies)

Manchester - Newcastle : 108 miles
Newcastle - Edinburgh : 90 miles
Edinburgh - Glasgow : 49 miles


 

 



The 3 Teams involved in Stage 1, each working 34miles of the route, taking 3.5 yrs to complete.

 

 


Beyond Stage 2: Extending the network




 

 

 

 

 

 

 

 

 

 

 


SMT Maglev Train, Long Yang road station
Shanghai. Photo : Transrapid rail.